ID |
Task Name |
Duration |
Start |
Finish |
Resource Names |
% Complete |
1 |
Milestones |
93 days |
Thu 98-06-11 |
Mon 98-10-19 |
|
0% |
2 |
Start |
0 days |
Thu 98-06-11 |
Thu 98-06-11 |
|
0% |
3 |
Lifecycle Objectives Milestone |
0 days |
Wed 98-06-17 |
Wed 98-06-17 |
|
0% |
4 |
Lifecycle Architecture Milestone |
0 days |
Thu 98-08-20 |
Thu 98-08-20 |
|
0% |
5 |
Initial Operational Capability Milestone |
0 days |
Tue 98-10-06 |
Tue 98-10-06 |
|
0% |
6 |
Product Release Milestone |
0 days |
Mon 98-10-19 |
Mon 98-10-19 |
|
0% |
7 |
|
1 day |
Thu 98-06-11 |
Thu 98-06-11 |
|
0% |
8 |
Inception Phase |
5 days |
Thu 98-06-11 |
Wed 98-06-17 |
|
0% |
9 |
Preliminary Iteration |
5 days |
Thu 98-06-11 |
Wed 98-06-17 |
|
0% |
10 |
Business Modeling |
3 days |
Thu 98-06-11 |
Mon 98-06-15 |
|
0% |
11 |
Capture a Common Vocabulary |
3 days |
Thu 98-06-11 |
Mon 98-06-15 |
Business-Process Analyst |
0% |
12 |
Find Business Actors and Use Cases |
3 days |
Thu 98-06-11 |
Mon 98-06-15 |
Business-Process Analyst |
0% |
13 |
Describe Business Use Cases |
1 day |
Thu 98-06-11 |
Thu 98-06-11 |
|
0% |
14 |
Describe Business Use Case 'BUC1' |
1 day |
Thu 98-06-11 |
Thu 98-06-11 |
Business Designer |
0% |
15 |
Describe Business Use Case 'BUC2' |
1 day |
Thu 98-06-11 |
Thu 98-06-11 |
Business Designer |
0% |
16 |
Structure the Business Use-Case Model |
2 days |
Thu 98-06-11 |
Fri 98-06-12 |
Business-Process Analyst |
0% |
17 |
Review Business Use-Case Model |
1 day |
Mon 98-06-15 |
Mon 98-06-15 |
Business-Model Reviewer |
0% |
18 |
Requirements |
5 days |
Thu 98-06-11 |
Wed 98-06-17 |
|
0% |
19 |
Develop Vision |
1 day |
Thu 98-06-11 |
Thu 98-06-11 |
System Analyst |
0% |
20 |
Elicit Stakeholder Needs |
1 day |
Fri 98-06-12 |
Fri 98-06-12 |
System Analyst |
0% |
21 |
Manage Dependencies |
5 days |
Thu 98-06-11 |
Wed 98-06-17 |
System Analyst |
0% |
22 |
Capture a Common Vocabulary |
5 days |
Thu 98-06-11 |
Wed 98-06-17 |
System Analyst |
0% |
23 |
Find Actors and Use Cases |
5 days |
Thu 98-06-11 |
Wed 98-06-17 |
System Analyst |
0% |
24 |
Prioritize Use Cases |
1 day |
Wed 98-06-17 |
Wed 98-06-17 |
Architect |
0% |
25 |
Define System & Constraints |
1 day |
Tue 98-06-16 |
Tue 98-06-16 |
System Analyst |
0% |
26 |
Configuration Management |
5 days |
Thu 98-06-11 |
Wed 98-06-17 |
|
0% |
27 |
Establish CM Practices |
1 day |
Thu 98-06-11 |
Thu 98-06-11 |
Project Manager |
0% |
28 |
Establish the CM Environment |
4 days |
Fri 98-06-12 |
Wed 98-06-17 |
Configuration Manager |
0% |
29 |
Management |
5 days |
Thu 98-06-11 |
Wed 98-06-17 |
|
0% |
30 |
Identify Risks |
5 days |
Thu 98-06-11 |
Wed 98-06-17 |
Project Manager |
0% |
31 |
Develop Project/Phase Plan |
1 day |
Thu 98-06-11 |
Thu 98-06-11 |
Project Manager |
0% |
32 |
Staff Project |
1 day |
Fri 98-06-12 |
Fri 98-06-12 |
Project Manager |
0% |
33 |
Generate Business Case |
1 day |
Mon 98-06-15 |
Mon 98-06-15 |
Project Manager |
0% |
34 |
|
1 day |
Thu 98-06-11 |
Thu 98-06-11 |
|
0% |
35 |
Elaboration Phase |
46 days |
Thu 98-06-18 |
Thu 98-08-20 |
|
0% |
36 |
Iteration 1 |
23 days |
Thu 98-06-18 |
Mon 98-07-20 |
|
0% |
37 |
Business Modeling |
3 days |
Fri 98-06-19 |
Tue 98-06-23 |
|
0% |
38 |
Find Business Workers and Entities |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
Business Designer |
0% |
39 |
Describe Business Workers |
1 day |
Mon 98-06-22 |
Mon 98-06-22 |
|
0% |
40 |
Describe Business Worker 'BW1' |
1 day |
Mon 98-06-22 |
Mon 98-06-22 |
Business Designer |
0% |
41 |
Describe Business Worker 'BW2' |
1 day |
Mon 98-06-22 |
Mon 98-06-22 |
Business Designer |
0% |
42 |
Describe Business Entities |
1 day |
Mon 98-06-22 |
Mon 98-06-22 |
|
0% |
43 |
Describe Business Entity 'BE1' |
1 day |
Mon 98-06-22 |
Mon 98-06-22 |
Business Designer |
0% |
44 |
Describe Business Entity 'BE2' |
1 day |
Mon 98-06-22 |
Mon 98-06-22 |
Business Designer |
0% |
45 |
Review the Business Object Model |
1 day |
Tue 98-06-23 |
Tue 98-06-23 |
Business-Model Reviewer |
0% |
46 |
Requirements |
5 days |
Fri 98-06-19 |
Thu 98-06-25 |
|
0% |
47 |
Manage Dependencies |
5 days |
Fri 98-06-19 |
Thu 98-06-25 |
System Analyst |
0% |
48 |
Detail Prioritized Use Cases |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
|
0% |
49 |
Detail Use Case 'UC1' |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
Use-Case Author |
0% |
50 |
Detal Use Case 'UC2' |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
Use-Case Author |
0% |
51 |
Detail Use Case 'UC3' |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
Use-Case Author |
0% |
52 |
Detail Use Case 'UC4' |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
Use-Case Author |
0% |
53 |
Detail Use Case 'UC5' |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
Use-Case Author |
0% |
54 |
Structure the Use Case Model |
1 day |
Mon 98-06-22 |
Mon 98-06-22 |
Architect |
0% |
55 |
User-Interface Modeling |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
User-Interface Designer |
0% |
56 |
User-Interface Prototyping |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
User-Interface Designer |
0% |
57 |
Review Requirements |
1 day |
Tue 98-06-23 |
Tue 98-06-23 |
Requirements Reviewer |
0% |
58 |
Analysis & Design (Architecture & Major
Risks) |
10 days |
Tue 98-06-23 |
Mon 98-07-06 |
|
0% |
59 |
Architectural Analysis |
1 day |
Tue 98-06-23 |
Tue 98-06-23 |
Architect |
0% |
60 |
Prioritized Use-Case Analysis |
1 day |
Wed 98-06-24 |
Wed 98-06-24 |
|
0% |
61 |
Analyze Use-Case 'UC1' |
1 day |
Wed 98-06-24 |
Wed 98-06-24 |
Designer |
0% |
62 |
Analyze Use-Case 'UC2' |
1 day |
Wed 98-06-24 |
Wed 98-06-24 |
Designer |
0% |
63 |
Analyze Use-Case 'UC3' |
1 day |
Wed 98-06-24 |
Wed 98-06-24 |
Designer |
0% |
64 |
Analyze Use-Case 'UC4' |
1 day |
Wed 98-06-24 |
Wed 98-06-24 |
Designer |
0% |
65 |
Architectural Design |
1 day |
Thu 98-06-25 |
Thu 98-06-25 |
|
0% |
66 |
Describe Concurrency |
1 day |
Fri 98-06-26 |
Fri 98-06-26 |
Architect |
0% |
67 |
Describe Distribution |
1 day |
Mon 98-06-29 |
Mon 98-06-29 |
Architect |
0% |
68 |
Review the Architecture |
1 day |
Tue 98-06-30 |
Tue 98-06-30 |
Architecture Reviewer |
0% |
69 |
Prioritized Subsystem Design |
1 day |
Wed 98-07-01 |
Wed 98-07-01 |
|
0% |
70 |
Subsystem Design - Subsystem 'S1' |
1 day |
Wed 98-07-01 |
Wed 98-07-01 |
Designer |
0% |
71 |
Subsystem Design - Subsystem 'S2' |
1 day |
Wed 98-07-01 |
Wed 98-07-01 |
Designer |
0% |
72 |
Prioritized Class Design |
1 day |
Wed 98-07-01 |
Wed 98-07-01 |
|
0% |
73 |
Class Design - Class 'C1' |
1 day |
Wed 98-07-01 |
Wed 98-07-01 |
Designer |
0% |
74 |
Class Design - Class 'C2' |
1 day |
Wed 98-07-01 |
Wed 98-07-01 |
Designer |
0% |
75 |
Class Design - Class 'C3' |
1 day |
Wed 98-07-01 |
Wed 98-07-01 |
Designer |
0% |
76 |
Class Design - Class 'C4' |
1 day |
Wed 98-07-01 |
Wed 98-07-01 |
Designer |
0% |
77 |
Prioritized Use-Case Design |
1 day |
Thu 98-07-02 |
Thu 98-07-02 |
|
0% |
78 |
Design Use-Case 'UC1' |
1 day |
Thu 98-07-02 |
Thu 98-07-02 |
Designer |
0% |
79 |
Design Use-Case 'UC2' |
1 day |
Thu 98-07-02 |
Thu 98-07-02 |
Designer |
0% |
80 |
Database Design |
1 day |
Fri 98-07-03 |
Fri 98-07-03 |
Database Designer |
0% |
81 |
Review the Design |
1 day |
Mon 98-07-06 |
Mon 98-07-06 |
Design Reviewer |
0% |
82 |
Implementation (Architecture & Major Risks) |
8 days |
Wed 98-07-01 |
Fri 98-07-10 |
|
0% |
83 |
Structure the Implementation Model |
1 day |
Wed 98-07-01 |
Wed 98-07-01 |
Architect |
0% |
84 |
Plan System Integration |
1 day |
Tue 98-07-07 |
Tue 98-07-07 |
System Integrator |
0% |
85 |
Plan Subsystem Integration |
1 day |
Wed 98-07-08 |
Wed 98-07-08 |
Implementer |
0% |
86 |
Implement Prioritized Components |
1 day |
Wed 98-07-08 |
Wed 98-07-08 |
|
0% |
87 |
Implement Component 'c1' |
1 day |
Wed 98-07-08 |
Wed 98-07-08 |
Implementer |
0% |
88 |
Implement Component 'c2' |
1 day |
Wed 98-07-08 |
Wed 98-07-08 |
Implementer |
0% |
89 |
Implement Component 'c3' |
1 day |
Wed 98-07-08 |
Wed 98-07-08 |
Implementer |
0% |
90 |
Implement Component 'c4' |
1 day |
Wed 98-07-08 |
Wed 98-07-08 |
Implementer |
0% |
91 |
Fix Defects |
1 day |
Thu 98-07-09 |
Thu 98-07-09 |
Implementer |
0% |
92 |
Integrate Subsystems |
1 day |
Thu 98-07-09 |
Thu 98-07-09 |
Implementer |
0% |
93 |
Integrate System |
1 day |
Fri 98-07-10 |
Fri 98-07-10 |
System Integrator |
0% |
94 |
Test (Architecture & Major Risks) |
7 days |
Wed 98-07-08 |
Thu 98-07-16 |
|
0% |
95 |
Plan Test (Integration & System) |
1 day |
Wed 98-07-08 |
Wed 98-07-08 |
Test Designer |
0% |
96 |
Design Test (Integration & System) |
1 day |
Thu 98-07-09 |
Thu 98-07-09 |
Test Designer |
0% |
97 |
Implement Test |
1 day |
Fri 98-07-10 |
Fri 98-07-10 |
Test Designer |
0% |
98 |
Design Test Packages and Classes |
1 day |
Mon 98-07-13 |
Mon 98-07-13 |
Designer |
0% |
99 |
Implement Test Components and Subsystems |
1 day |
Tue 98-07-14 |
Tue 98-07-14 |
Implementer |
0% |
100 |
Execute Integration Test |
1 day |
Wed 98-07-15 |
Wed 98-07-15 |
Integration Tester |
0% |
101 |
Execute System Test |
1 day |
Thu 98-07-16 |
Thu 98-07-16 |
System Tester |
0% |
102 |
Execute Performance Tests |
1 day |
Wed 98-07-15 |
Wed 98-07-15 |
Performance Tester |
0% |
103 |
Evaluate Test |
1 day |
Thu 98-07-16 |
Thu 98-07-16 |
Test Designer |
0% |
104 |
Management |
23 days |
Thu 98-06-18 |
Mon 98-07-20 |
|
0% |
105 |
Develop Iteration Plan |
1 day |
Thu 98-06-18 |
Thu 98-06-18 |
Project Manager |
0% |
106 |
Staff the Project |
1 day |
Fri 98-06-19 |
Fri 98-06-19 |
Project Manager |
0% |
107 |
Revisit Risk List |
21 days |
Thu 98-06-18 |
Thu 98-07-16 |
Project Manager |
0% |
108 |
Evaluate the Iteration |
1 day |
Fri 98-07-17 |
Fri 98-07-17 |
Project Manager |
0% |
109 |
Update Project Plan |
1 day |
Mon 98-07-20 |
Mon 98-07-20 |
Project Manager |
0% |
110 |
Iteration 2 |
23 days |
Tue 98-07-21 |
Thu 98-08-20 |
|
0% |
111 |
Requirements (Stabilize) |
3 days |
Wed 98-07-22 |
Fri 98-07-24 |
|
0% |
112 |
Manage Dependencies |
3 days |
Wed 98-07-22 |
Fri 98-07-24 |
System Analyst |
0% |
113 |
Detail Prioritized Use Cases |
1 day |
Wed 98-07-22 |
Wed 98-07-22 |
|
0% |
114 |
Detail Use Case 'UC6' |
1 day |
Wed 98-07-22 |
Wed 98-07-22 |
Use-Case Author |
0% |
115 |
Detal Use Case 'UC7' |
1 day |
Wed 98-07-22 |
Wed 98-07-22 |
Use-Case Author |
0% |
116 |
Detail Use Case 'UC8' |
1 day |
Wed 98-07-22 |
Wed 98-07-22 |
Use-Case Author |
0% |
117 |
Detail Use Case 'UC9' |
1 day |
Wed 98-07-22 |
Wed 98-07-22 |
Use-Case Author |
0% |
118 |
Detail Use Case 'UC10' |
1 day |
Wed 98-07-22 |
Wed 98-07-22 |
Use-Case Author |
0% |
119 |
Structure the Use Case Model |
1 day |
Thu 98-07-23 |
Thu 98-07-23 |
Architect |
0% |
120 |
User-Interface Modeling |
1 day |
Wed 98-07-22 |
Wed 98-07-22 |
User-Interface Designer |
0% |
121 |
User-Interface Prototyping |
1 day |
Wed 98-07-22 |
Wed 98-07-22 |
User-Interface Designer |
0% |
122 |
Review Requirements |
1 day |
Fri 98-07-24 |
Fri 98-07-24 |
Requirements Reviewer |
0% |
123 |
Analysis & Design (Architecture & Major
Risks) |
10 days |
Fri 98-07-24 |
Thu 98-08-06 |
|
0% |
124 |
Architectural Analysis |
1 day |
Fri 98-07-24 |
Fri 98-07-24 |
Architect |
0% |
125 |
Prioritized Use-Case Analysis |
1 day |
Mon 98-07-27 |
Mon 98-07-27 |
|
0% |
126 |
Analyze Use-Case 'UC5' |
1 day |
Mon 98-07-27 |
Mon 98-07-27 |
Designer |
0% |
127 |
Analyze Use-Case 'UC6' |
1 day |
Mon 98-07-27 |
Mon 98-07-27 |
Designer |
0% |
128 |
Analyze Use-Case 'UC7' |
1 day |
Mon 98-07-27 |
Mon 98-07-27 |
Designer |
0% |
129 |
Analyze Use-Case 'UC8' |
1 day |
Mon 98-07-27 |
Mon 98-07-27 |
Designer |
0% |
130 |
Analyze Use-Case 'UC9' |
1 day |
Mon 98-07-27 |
Mon 98-07-27 |
Designer |
0% |
131 |
Analyze Use-Case 'UC10' |
1 day |
Mon 98-07-27 |
Mon 98-07-27 |
Designer |
0% |
132 |
Architectural Design |
1 day |
Tue 98-07-28 |
Tue 98-07-28 |
Architect |
0% |
133 |
Describe Concurrency |
1 day |
Wed 98-07-29 |
Wed 98-07-29 |
Architect |
0% |
134 |
Describe Distribution |
1 day |
Thu 98-07-30 |
Thu 98-07-30 |
Architect |
0% |
135 |
Review the Architecture |
1 day |
Fri 98-07-31 |
Fri 98-07-31 |
Architecture Reviewer |
0% |
136 |
Prioritized Subsystem Design |
1 day |
Mon 98-08-03 |
Mon 98-08-03 |
|
0% |
137 |
Subsystem Design - Subsystem 'S3' |
1 day |
Mon 98-08-03 |
Mon 98-08-03 |
Designer |
0% |
138 |
Subsystem Design - Subsystem 'S4' |
1 day |
Mon 98-08-03 |
Mon 98-08-03 |
Designer |
0% |
139 |
Prioritized Class Design |
1 day |
Mon 98-08-03 |
Mon 98-08-03 |
|
0% |
140 |
Class Design - Class 'C5' |
1 day |
Mon 98-08-03 |
Mon 98-08-03 |
Designer |
0% |
141 |
Class Design - Class 'C6' |
1 day |
Mon 98-08-03 |
Mon 98-08-03 |
Designer |
0% |
142 |
Class Design - Class 'C7' |
1 day |
Mon 98-08-03 |
Mon 98-08-03 |
Designer |
0% |
143 |
Class Design - Class 'C8' |
1 day |
Mon 98-08-03 |
Mon 98-08-03 |
Designer |
0% |
144 |
Prioritized Use-Case Design |
1 day |
Tue 98-08-04 |
Tue 98-08-04 |
Designer |
0% |
145 |
Design Use-Case 'UC3' |
1 day |
Tue 98-08-04 |
Tue 98-08-04 |
Designer |
0% |
146 |
Design Use-Case 'UC6' |
1 day |
Tue 98-08-04 |
Tue 98-08-04 |
Designer |
0% |
147 |
Database Design |
1 day |
Wed 98-08-05 |
Wed 98-08-05 |
Database Designer |
0% |
148 |
Review the Design |
1 day |
Thu 98-08-06 |
Thu 98-08-06 |
Design Reviewer |
0% |
149 |
Implementation (Architecture & Major Risks) |
8 days |
Mon 98-08-03 |
Wed 98-08-12 |
|
0% |
150 |
Structure the Implementation Model |
1 day |
Mon 98-08-03 |
Mon 98-08-03 |
Architect |
0% |
151 |
Plan System Integration |
1 day |
Fri 98-08-07 |
Fri 98-08-07 |
System Integrator |
0% |
152 |
Plan Subsystem Integration |
1 day |
Mon 98-08-10 |
Mon 98-08-10 |
Implementer |
0% |
153 |
Implement Prioritized Components |
1 day |
Mon 98-08-10 |
Mon 98-08-10 |
|
0% |
154 |
Implement Component 'c5' |
1 day |
Mon 98-08-10 |
Mon 98-08-10 |
Implementer |
0% |
155 |
Implement Component 'c6' |
1 day |
Mon 98-08-10 |
Mon 98-08-10 |
Implementer |
0% |
156 |
Implement Component 'c7' |
1 day |
Mon 98-08-10 |
Mon 98-08-10 |
Implementer |
0% |
157 |
Implement Component 'c8' |
1 day |
Mon 98-08-10 |
Mon 98-08-10 |
Implementer |
0% |
158 |
Fix Defects |
1 day |
Tue 98-08-11 |
Tue 98-08-11 |
Implementer |
0% |
159 |
Integrate Subsystems |
1 day |
Tue 98-08-11 |
Tue 98-08-11 |
Implementer |
0% |
160 |
Integrate System |
1 day |
Wed 98-08-12 |
Wed 98-08-12 |
System Integrator |
0% |
161 |
Test (Architecture & Major Risks) |
7 days |
Mon 98-08-10 |
Tue 98-08-18 |
|
0% |
162 |
Plan Test (Integration & System) |
1 day |
Mon 98-08-10 |
Mon 98-08-10 |
Test Designer |
0% |
163 |
Design Test (Integration & System) |
1 day |
Tue 98-08-11 |
Tue 98-08-11 |
Test Designer |
0% |
164 |
Implement Test |
1 day |
Wed 98-08-12 |
Wed 98-08-12 |
Test Designer |
0% |
165 |
Design Test Packages and Classes |
1 day |
Thu 98-08-13 |
Thu 98-08-13 |
Designer |
0% |
166 |
Implement Test Components and Subsystems |
1 day |
Fri 98-08-14 |
Fri 98-08-14 |
Implementer |
0% |
167 |
Execute Integration Test |
1 day |
Mon 98-08-17 |
Mon 98-08-17 |
Integration Tester |
0% |
168 |
Execute System Test |
1 day |
Tue 98-08-18 |
Tue 98-08-18 |
System Tester |
0% |
169 |
Execute Performance Tests |
1 day |
Mon 98-08-17 |
Mon 98-08-17 |
Performance Tester |
0% |
170 |
Evaluate Test |
1 day |
Tue 98-08-18 |
Tue 98-08-18 |
Test Designer |
0% |
171 |
Management |
23 days |
Tue 98-07-21 |
Thu 98-08-20 |
|
0% |
172 |
Develop Iteration Plan |
1 day |
Tue 98-07-21 |
Tue 98-07-21 |
Project Manager |
0% |
173 |
Staff Project |
1 day |
Wed 98-07-22 |
Wed 98-07-22 |
Project Manager |
0% |
174 |
Revisit Risk List |
22 days |
Tue 98-07-21 |
Wed 98-08-19 |
Project Manager |
0% |
175 |
Evaluate the Iteration |
1 day |
Wed 98-08-19 |
Wed 98-08-19 |
Project Manager |
0% |
176 |
Update Project Plan |
1 day |
Thu 98-08-20 |
Thu 98-08-20 |
Project Manager |
0% |
177 |
|
1 day |
Tue 98-07-21 |
Tue 98-07-21 |
|
0% |
178 |
Construction Phase |
33 days |
Fri 98-08-21 |
Tue 98-10-06 |
|
0% |
179 |
Iteration n |
11 days |
Fri 98-08-21 |
Fri 98-09-04 |
|
0% |
180 |
Analysis & Design (Refine) |
4 days |
Mon 98-08-24 |
Thu 98-08-27 |
|
0% |
181 |
Refine Architecture |
4 days |
Mon 98-08-24 |
Thu 98-08-27 |
Architect |
0% |
182 |
Prioritized Subsystem Design |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
|
0% |
183 |
Subsystem Design - Subsystem 'S5' |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Designer |
0% |
184 |
Subsystem Design - Subsystem 'S6' |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Designer |
0% |
185 |
Prioritized Class Design |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
|
0% |
186 |
Class Design - Class 'C9' |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Designer |
0% |
187 |
Class Design - Class 'C10' |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Designer |
0% |
188 |
Class Design - Class 'C11' |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Designer |
0% |
189 |
Class Design - Class 'C12' |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Designer |
0% |
190 |
Class Design - Class 'C13' |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Designer |
0% |
191 |
Class Design - Class 'C14' |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Designer |
0% |
192 |
Prioritized Use-Case Design |
1 day |
Tue 98-08-25 |
Tue 98-08-25 |
|
0% |
193 |
Design Use-Case 'UC4' |
1 day |
Tue 98-08-25 |
Tue 98-08-25 |
Designer |
0% |
194 |
Design Use-Case 'UC5' |
1 day |
Tue 98-08-25 |
Tue 98-08-25 |
Designer |
0% |
195 |
Design Use-Case 'UC7' |
1 day |
Tue 98-08-25 |
Tue 98-08-25 |
Designer |
0% |
196 |
Database Design |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
Database Designer |
0% |
197 |
Review the Design |
1 day |
Thu 98-08-27 |
Thu 98-08-27 |
Design Reviewer |
0% |
198 |
Implementation (Effective Production) |
6 days |
Mon 98-08-24 |
Mon 98-08-31 |
|
0% |
199 |
Plan System Integration |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
System Integrator |
0% |
200 |
Plan Subsystem Integration |
1 day |
Tue 98-08-25 |
Tue 98-08-25 |
Implementer |
0% |
201 |
Implement Prioritized Components |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
|
0% |
202 |
Implement Component 'c9' |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
Implementer |
0% |
203 |
Implement Component 'c10' |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
Implementer |
0% |
204 |
Implement Component 'c11' |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
Implementer |
0% |
205 |
Implement Component 'c12' |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
Implementer |
0% |
206 |
Implement Component 'c13' |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
Implementer |
0% |
207 |
Implement Component 'c14' |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
Implementer |
0% |
208 |
Fix Defects |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
Implementer |
0% |
209 |
Review Code |
1 day |
Thu 98-08-27 |
Thu 98-08-27 |
Code Reviewer |
0% |
210 |
Perform Unit Tests |
1 day |
Thu 98-08-27 |
Thu 98-08-27 |
Implementer |
0% |
211 |
Integrate Subsystem |
1 day |
Fri 98-08-28 |
Fri 98-08-28 |
Implementer |
0% |
212 |
Integrate System |
1 day |
Mon 98-08-31 |
Mon 98-08-31 |
System Integrator |
0% |
213 |
Test (Interfaces & Integrated Function) |
8 days |
Mon 98-08-24 |
Wed 98-09-02 |
|
0% |
214 |
Plan Test (Integration & System) |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Test Designer |
0% |
215 |
Design Test (Integration & System) |
1 day |
Tue 98-08-25 |
Tue 98-08-25 |
Test Designer |
0% |
216 |
Implement Test |
1 day |
Wed 98-08-26 |
Wed 98-08-26 |
Test Designer |
0% |
217 |
Design Test Packages and Classes |
1 day |
Thu 98-08-27 |
Thu 98-08-27 |
Designer |
0% |
218 |
Implement Test Components and Subsystems |
1 day |
Fri 98-08-28 |
Fri 98-08-28 |
Implementer |
0% |
219 |
Execute Integration Tests |
1 day |
Mon 98-08-31 |
Mon 98-08-31 |
Integration Tester |
0% |
220 |
Execute System Test |
1 day |
Tue 98-09-01 |
Tue 98-09-01 |
System Tester |
0% |
221 |
Execute Performance Tests |
1 day |
Mon 98-08-31 |
Mon 98-08-31 |
Performance Tester |
0% |
222 |
Evaluate Test |
1 day |
Wed 98-09-02 |
Wed 98-09-02 |
Test Designer |
0% |
223 |
Management |
11 days |
Fri 98-08-21 |
Fri 98-09-04 |
|
0% |
224 |
Develop Iteration Plan |
1 day |
Fri 98-08-21 |
Fri 98-08-21 |
Project Manager |
0% |
225 |
Staff Project |
1 day |
Mon 98-08-24 |
Mon 98-08-24 |
Project Manager |
0% |
226 |
Revisit Risk List |
11 days |
Fri 98-08-21 |
Fri 98-09-04 |
Project Manager |
0% |
227 |
Evaluate the Iteration |
1 day |
Thu 98-09-03 |
Thu 98-09-03 |
Project Manager |
0% |
228 |
Update Project Plan |
1 day |
Fri 98-09-04 |
Fri 98-09-04 |
Project Manager |
0% |
229 |
Iteration n+1 |
11 days |
Mon 98-09-07 |
Mon 98-09-21 |
|
0% |
230 |
Analysis & Design (Refine) |
4 days |
Tue 98-09-08 |
Fri 98-09-11 |
|
0% |
231 |
Refine Architecture |
4 days |
Tue 98-09-08 |
Fri 98-09-11 |
Architect |
0% |
232 |
Prioritized Subsystem Design |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
Designer |
0% |
233 |
Subsystem Design - Subsystem 'S7' |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
|
0% |
234 |
Subsystem Design - Subsystem 'S8' |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
|
0% |
235 |
Prioritized Class Design |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
|
0% |
236 |
Class Design - Class 'C15' |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
Designer |
0% |
237 |
Class Design - Class 'C16' |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
Designer |
0% |
238 |
Class Design - Class 'C17' |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
Designer |
0% |
239 |
Class Design - Class 'C18' |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
Designer |
0% |
240 |
Class Design - Class 'C19' |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
Designer |
0% |
241 |
Class Design - Class 'C20' |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
Designer |
0% |
242 |
Prioritized Use-Case Design |
1 day |
Wed 98-09-09 |
Wed 98-09-09 |
Designer |
0% |
243 |
Design Use-Case 'UC8' |
1 day |
Wed 98-09-09 |
Wed 98-09-09 |
Designer |
0% |
244 |
Design Use-Case 'UC9' |
1 day |
Wed 98-09-09 |
Wed 98-09-09 |
Designer |
0% |
245 |
Database Design |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
Database Designer |
0% |
246 |
Review the Design |
1 day |
Fri 98-09-11 |
Fri 98-09-11 |
Design Reviewer |
0% |
247 |
Implementation (Effective Production) |
6 days |
Tue 98-09-08 |
Tue 98-09-15 |
|
0% |
248 |
Plan System Integration |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
System Integrator |
0% |
249 |
Plan Subsystem Integration |
1 day |
Wed 98-09-09 |
Wed 98-09-09 |
Implementer |
0% |
250 |
Implement Prioritized Components |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
|
0% |
251 |
Implement Component 'c15' |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
Implementer |
0% |
252 |
Implement Component 'c16' |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
Implementer |
0% |
253 |
Implement Component 'c17' |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
Implementer |
0% |
254 |
Implement Component 'c18' |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
Implementer |
0% |
255 |
Implement Component 'c19' |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
Implementer |
0% |
256 |
Implement Component 'c20' |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
Implementer |
0% |
257 |
Fix Defects |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
Implementer |
0% |
258 |
Review Code |
1 day |
Fri 98-09-11 |
Fri 98-09-11 |
Code Reviewer |
0% |
259 |
Perform Unit Tests |
1 day |
Fri 98-09-11 |
Fri 98-09-11 |
Implementer |
0% |
260 |
Integrate Subsystem |
1 day |
Mon 98-09-14 |
Mon 98-09-14 |
Implementer |
0% |
261 |
Integrate System |
1 day |
Tue 98-09-15 |
Tue 98-09-15 |
System Integrator |
0% |
262 |
Test (Interfaces & Integrated Function) |
8 days |
Tue 98-09-08 |
Thu 98-09-17 |
|
0% |
263 |
Plan Test (Integration & System) |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
Test Designer |
0% |
264 |
Design Test (Integration & System) |
1 day |
Wed 98-09-09 |
Wed 98-09-09 |
Test Designer |
0% |
265 |
Implement Test |
1 day |
Thu 98-09-10 |
Thu 98-09-10 |
Test Designer |
0% |
266 |
Design Test Packages and Classes |
1 day |
Fri 98-09-11 |
Fri 98-09-11 |
Designer |
0% |
267 |
Implement Test Components and Subsystems |
1 day |
Mon 98-09-14 |
Mon 98-09-14 |
Implementer |
0% |
268 |
Execute Integration Tests |
1 day |
Tue 98-09-15 |
Tue 98-09-15 |
Integration Tester |
0% |
269 |
Execute System Test |
1 day |
Wed 98-09-16 |
Wed 98-09-16 |
System Tester |
0% |
270 |
Execute Performance Tests |
1 day |
Tue 98-09-15 |
Tue 98-09-15 |
Performance Tester |
0% |
271 |
Evaluate Test |
1 day |
Thu 98-09-17 |
Thu 98-09-17 |
Test Designer |
0% |
272 |
Management |
11 days |
Mon 98-09-07 |
Mon 98-09-21 |
|
0% |
273 |
Develop Iteration Plan |
1 day |
Mon 98-09-07 |
Mon 98-09-07 |
Project Manager |
0% |
274 |
Staff Project |
1 day |
Tue 98-09-08 |
Tue 98-09-08 |
Project Manager |
0% |
275 |
Revisit Risk List |
11 days |
Mon 98-09-07 |
Mon 98-09-21 |
Project Manager |
0% |
276 |
Evaluate the Iteration |
1 day |
Fri 98-09-18 |
Fri 98-09-18 |
Project Manager |
0% |
277 |
Update Project Plan |
1 day |
Mon 98-09-21 |
Mon 98-09-21 |
Project Manager |
0% |
278 |
Iteration n+2 |
11 days |
Tue 98-09-22 |
Tue 98-10-06 |
|
0% |
279 |
Analysis & Design (Refine) |
4 days |
Wed 98-09-23 |
Mon 98-09-28 |
|
0% |
280 |
Refine Architecture |
4 days |
Wed 98-09-23 |
Mon 98-09-28 |
Architect |
0% |
281 |
Prioritized Subsystem Design |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
Designer |
0% |
282 |
Subsystem Design - Subsystem 'S9' |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
|
0% |
283 |
Subsystem Design - Subsystem 'S10' |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
|
0% |
284 |
Prioritized Class Design |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
|
0% |
285 |
Class Design - Class 'C21' |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
Designer |
0% |
286 |
Class Design - Class 'C22' |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
Designer |
0% |
287 |
Class Design - Class 'C23' |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
Designer |
0% |
288 |
Class Design - Class 'C24' |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
Designer |
0% |
289 |
Class Design - Class 'C25' |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
Designer |
0% |
290 |
Class Design - Class 'C26' |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
Designer |
0% |
291 |
Prioritized Use-Case Design |
1 day |
Thu 98-09-24 |
Thu 98-09-24 |
Designer |
0% |
292 |
Design Use-Case 'UC10' |
1 day |
Thu 98-09-24 |
Thu 98-09-24 |
Designer |
0% |
293 |
Database Design |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
Database Designer |
0% |
294 |
Review the Design |
1 day |
Mon 98-09-28 |
Mon 98-09-28 |
Design Reviewer |
0% |
295 |
Implementation (Effective Production) |
6 days |
Wed 98-09-23 |
Wed 98-09-30 |
|
0% |
296 |
Plan System Integration |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
System Integrator |
0% |
297 |
Plan Subsystem Integration |
1 day |
Thu 98-09-24 |
Thu 98-09-24 |
Implementer |
0% |
298 |
Implement Prioritized Components |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
|
0% |
299 |
Implement Component 'c21' |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
Implementer |
0% |
300 |
Implement Component 'c22' |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
Implementer |
0% |
301 |
Implement Component 'c23' |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
Implementer |
0% |
302 |
Implement Component 'c24' |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
Implementer |
0% |
303 |
Implement Component 'c25' |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
Implementer |
0% |
304 |
Implement Component 'c26' |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
Implementer |
0% |
305 |
Fix Defects |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
Implementer |
0% |
306 |
Review Code |
1 day |
Mon 98-09-28 |
Mon 98-09-28 |
Code Reviewer |
0% |
307 |
Perform Unit Tests |
1 day |
Mon 98-09-28 |
Mon 98-09-28 |
Implementer |
0% |
308 |
Integrate Subsystem |
1 day |
Tue 98-09-29 |
Tue 98-09-29 |
Implementer |
0% |
309 |
Integrate System |
1 day |
Wed 98-09-30 |
Wed 98-09-30 |
System Integrator |
0% |
310 |
Test (Interfaces & Integrated Function) |
8 days |
Wed 98-09-23 |
Fri 98-10-02 |
|
0% |
311 |
Plan Test (Integration & System) |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
Test Designer |
0% |
312 |
Design Test (Integration & System) |
1 day |
Thu 98-09-24 |
Thu 98-09-24 |
Test Designer |
0% |
313 |
Implement Test |
1 day |
Fri 98-09-25 |
Fri 98-09-25 |
Test Designer |
0% |
314 |
Design Test Packages and Classes |
1 day |
Mon 98-09-28 |
Mon 98-09-28 |
Designer |
0% |
315 |
Implement Test Components and Subsystems |
1 day |
Tue 98-09-29 |
Tue 98-09-29 |
Implementer |
0% |
316 |
Execute Integration Tests |
1 day |
Wed 98-09-30 |
Wed 98-09-30 |
Integration Tester |
0% |
317 |
Execute System Test |
1 day |
Thu 98-10-01 |
Thu 98-10-01 |
System Tester |
0% |
318 |
Execute Performance Tests |
1 day |
Wed 98-09-30 |
Wed 98-09-30 |
Performance Tester |
0% |
319 |
Evaluate Test |
1 day |
Fri 98-10-02 |
Fri 98-10-02 |
Test Designer |
0% |
320 |
Management |
11 days |
Tue 98-09-22 |
Tue 98-10-06 |
|
0% |
321 |
Develop Iteration Plan |
1 day |
Tue 98-09-22 |
Tue 98-09-22 |
Project Manager |
0% |
322 |
Staff Project |
1 day |
Wed 98-09-23 |
Wed 98-09-23 |
Project Manager |
0% |
323 |
Revisit Risk List |
11 days |
Tue 98-09-22 |
Tue 98-10-06 |
Project Manager |
0% |
324 |
Evaluate the Iteration |
1 day |
Mon 98-10-05 |
Mon 98-10-05 |
Project Manager |
0% |
325 |
Update Project Plan |
1 day |
Tue 98-10-06 |
Tue 98-10-06 |
Project Manager |
0% |
326 |
|
1 day |
Tue 98-09-22 |
Tue 98-09-22 |
|
0% |
327 |
Transition Phase |
9 days |
Wed 98-10-07 |
Mon 98-10-19 |
|
0% |
328 |
Iteration m |
9 days |
Wed 98-10-07 |
Mon 98-10-19 |
|
0% |
329 |
Deployment |
9 days |
Wed 98-10-07 |
Mon 98-10-19 |
|
0% |
330 |
Produce Software |
1 day |
Wed 98-10-07 |
Wed 98-10-07 |
|
0% |
331 |
Installation scripts |
1 day |
Wed 98-10-07 |
Wed 98-10-07 |
|
0% |
332 |
User documentation |
1 day |
Wed 98-10-07 |
Wed 98-10-07 |
|
0% |
333 |
Configuration data |
1 day |
Wed 98-10-07 |
Wed 98-10-07 |
|
0% |
334 |
Additional programs for migration: data conversion |
1 day |
Wed 98-10-07 |
Wed 98-10-07 |
|
0% |
335 |
Package Software |
1 day |
Thu 98-10-08 |
Thu 98-10-08 |
Deployment Manager |
0% |
336 |
Distribute Software |
1 day |
Fri 98-10-09 |
Fri 98-10-09 |
Deployment Manager |
0% |
337 |
Install Software |
1 day |
Mon 98-10-12 |
Mon 98-10-12 |
Deployment Manager |
0% |
338 |
Migration |
4 days |
Wed 98-10-14 |
Mon 98-10-19 |
Deployment Manager |
0% |
339 |
Provide Help and Assistance to the Users |
5 days |
Tue 98-10-13 |
Mon 98-10-19 |
Deployment Manager |
0% |
340 |
Acceptance Testing |
1 day |
Tue 98-10-13 |
Tue 98-10-13 |
Project Manager |
0% |
341 |
|
1 day |
Wed 98-10-07 |
Wed 98-10-07 |
|
0% |
342 |
Environment |
93 days |
Thu 98-06-11 |
Mon 98-10-19 |
|
0% |
343 |
Configure Processes |
20 days |
Thu 98-06-11 |
Wed 98-07-08 |
|
0% |
344 |
Improve Processes |
30 days |
Thu 98-07-09 |
Wed 98-08-19 |
|
0% |
345 |
Select and Acquire Tools |
30 days |
Thu 98-06-11 |
Wed 98-07-22 |
|
0% |
346 |
Toolsmithing |
30 days |
Thu 98-06-11 |
Wed 98-07-22 |
|
0% |
347 |
Support the Development |
93 days |
Thu 98-06-11 |
Mon 98-10-19 |
|
0% |
348 |
Training |
30 days |
Thu 98-06-11 |
Wed 98-07-22 |
|
0% |